Accelerating phase 2 of Japan – Hai Phong Industrial Park

BAO CHAU - TRUNG KIEN 10/09/2026 20:59

The investor of phase 2 of Japan - Hai Phong Industrial Park is accelerating construction, aiming to hand over the first land plot to a secondary investor in the 4th quarter of 2026.

Chủ đầu tư tổ chức thi công đồng thời nhiều hạng mục hạ tầng kỹ thuật.
The investor is carrying out multiple technical infrastructure works at the same time.

Multiple construction fronts

Phase 2 of Japan - Hai Phong Industrial Park, invested in by Hai Phong International Industrial Park JSC, is an expansion project following the success of phase 1.

The project covers 197.16 hectares in Hong An Ward, with a total investment of USD 170 million, contributing to promoting industrial development and realizing the goal of building Hai Phong into a modern industrial center of the northern region.

According to Pham Van Tuyen, Deputy General Director of Hai Phong International Industrial Park JSC, the company is focusing financial, human and equipment resources on the project while directing the general contractor and other contractors to increase manpower and machinery and organize multiple construction fronts simultaneously for site leveling, internal roads, power and water supply, drainage and other technical infrastructure works.

The company is stepping up investment promotion and working with many domestic and foreign investors, particularly Japanese ones. The project has received positive feedback and secured its first customers.

Chủ đầu tư dự án khẩn trương san lấp mặt bằng để giao đất cho nhà đầu tư thứ cấp.
The project investor is urgently leveling the site to hand over land to secondary investors.

In April 2026, Rorze Robotech Co., Ltd. signed a memorandum of understanding on leasing land and technical infrastructure. The investor is expected to hand over the first land plot by the end of the 4th quarter of 2026.

In addition, several strategic investors are studying the industrial park. The investor is expected to hand over an additional 54 hectares to secondary investors in 2027.

Timely removal of obstacles

Ensuring the progress of site clearance and construction of phase 2 of Japan - Hai Phong Industrial Park is important to achieving the objectives set out in the Municipal Party Committee’s Resolution No. 11-NQ/TU dated July 15, 2026 on strengthening leadership and direction to achieve an average annual GRDP growth rate of at least 13% in the last six months of 2026 and during the 2026 – 2030 period.

Phần diện tích đất hoàn thành giải phóng mặt bằng.
The area where site clearance has been completed.

At the end of August 2026, Vice Chairman of the Municipal People's Committee Tran Van Quan inspected several projects, including phase 2 of Japan - Hai Phong Industrial Park, and worked with Hong An Ward on the implementation of socio-economic development tasks and Resolution No. 11-NQ/TU.

Quan directed relevant departments and local authorities to remove the obstacles of the project, including issues related to transport connections and the relocation of fuel pipelines.

Nguyen Huu Thanh, Chairman of the Hong An Ward People's Committee, said the committee regularly reviewed and monitored project implementation and proactively coordinated with the city's specialized agencies and relevant units to carry out the project. Difficulties and obstacles within its jurisdiction were promptly compiled, reported and proposed for resolution, while favorable conditions were created for investors to accelerate project implementation.

The Ward People's Committee has handed over land to Hai Phong International Industrial Park JSC in three phases, totaling 57.2 hectares. The ward has committed to completing site clearance for the project by the 2nd quarter of 2027.

BAO CHAU - TRUNG KIEN