Construction units are working against the clock to complete three interchanges in central Hai Phong for opening to traffic in just over two months as scheduled.

Three construction sites enter the final push
At the construction site of the Bui Vien – Vo Nguyen Giap interchange, the contractor has completed waterproofing and concrete pouring for the retaining wall sections. Nearly one year after construction began on December 19, 2025, the project has entered its final construction phase, with work progressing urgently on concrete pouring for the enclosed underpass, the pumping station and various above-ground structures.
The Le Hong Phong – Bui Vien interchange project is also entering a phase of concentrated construction across its various components. However, its construction output is still falling short of the pace required to accelerate the schedule and open the underpass before the 2027 Lunar New Year.
Nguyen Manh Cuong, the project construction supervisor at Phuong Thanh Transport Investment and Construction JSC, said the contractor is currently operating four construction teams working continuously on enclosed and open-cut sections of the underpass. Excavation is followed immediately by the installation of support frames.

At the construction site of the Nguyen Trai – Le Hong Phong interchange, undertaken by a consortium comprising Thang Long Corporation JSC and Construction and Investment JSC No. 18, the project components are gradually taking shape. Numerous machines, engineers and workers have been mobilized to maintain progress. Construction teams are working continuously day and night despite relatively complex traffic conditions.
After nearly a year of construction, a lot of major components of the three underpass projects have been completed. The structures are gradually taking shape at the busy intersections in the heart of the port city.
Striving to remove bottlenecks
A comparison of progress across the three underpasses shows that the Le Hong Phong – Bui Vien interchange project faces greater disadvantages in accelerating construction. The site is located at a gateway to the seaport and Cat Bi International Airport, where traffic volumes are high but available space is relatively limited. It is also in a low-lying area that concentrates the drainage network for the entire Hai An area. Rainfall can therefore bring excavation and earthworks to an almost complete standstill.

To meet the target of completing the main components and opening the underpass before the 2027 Lunar New Year, Nguyen Manh Cuong said the contractor is recalculating and revising the schedule for each component. It is also mobilizing all skilled workers and equipment from other construction sites to reinforce the workforce. The goal is to complete excavation, earthworks and support-frame installation by early December, enabling concrete pouring for the base slab and retaining walls throughout the enclosed underpass.
According to the Hai Phong Traffic Construction Investment Project Management Board, the investor of all three underpass projects, maintaining progress requires contractors to review every project component and arrange sufficient workers, machinery and materials to carry out multiple construction operations simultaneously and systematically, particularly on items that determine the overall schedule. Contractors are required to submit daily reports to the investor on completed work volumes and any arising issues or requests. Determined not to allow any schedule delays, the investor has established critical-path schedules for each project. Meanwhile, construction units are continuing to accelerate work on technical infrastructure, ensuring that each completed section is tidied up and finalized before moving on.
There are just over 70 days left before the 2027 Lunar New Year. Although the three underpass projects have made encouraging progress, the construction sites continue to face pressure from material and labor shortages, as well as challenging working conditions. The three projects must not only maintain their pace but also strictly control construction quality and occupational safety. Once completed and opened to traffic, the underpasses are expected not only to ease congestion and reduce conflicts between traffic flows at the intersections but also to create distinctive urban architectural and landscape features.
PHAM CUONG – TRUNG KIEN