Removing site clearance bottlenecks for Thang Long industrial cluster
More than 12 hectares of land designated for infrastructure connectivity have yet to meet the legal requirements for land acquisition, causing prolonged site clearance delays at Thang Long Industrial Cluster and affecting the project’s overall progress.
News
Ensuring no bottlenecks in land procedures for people
After the National Assembly passed Resolution 254/2025, the Government issued Decree 50/2026 to address bottlenecks arising in the implementation of the Land Law 2024.
Removing bottlenecks, strengthening connectivity for FDI enterprises
Proactively accompanying foreign-invested (FDI) enterprises, the Hai Phong Department of Finance has jointly implemented a range of concrete solutions to promptly remove bottlenecks, strengthen connectivity, and attract investment.
Removing bottlenecks in site clearance to accelerate public investment disbursement
Vice Chairman of the Hai Phong People’s Committee Tran Van Quan has asked localities to continue reviewing and promptly addressing bottlenecks and obstacles in the process of compensation, support, and resettlement.
Hai Phong removes land bottlenecks to help SMEs break through
When having stable land premises, many small- and medium-sized enterprises (SMEs) in Hai Phong will boldly invest in technology, improve production capacity, and increase opportunities to participate more deeply in the global supply chain.
Unlocking private enterprises’ growth – Article 5: Clearing bottlenecks in preferential funding