road
Hai Phong Party chief encourages workers at key transport projects
10 days after Secretary of the Hai Phong Party Committee Le Ngoc Chau issued his directive, construction progress has increased at all five transport projects.
Business
Construction continues through holiday on Hai Phong's key projects
During this year's National Day holiday, thousands of engineers and workers remain diligently working at the construction sites of Hai Phong’s key projects.
Racing to complete Ring Road 2
The construction of the Tan Vu - Hung Dao - Bui Vien section of Ring Road 2 is being accelerated, with about 61.5% of the workload completed.
Following Uncle Ho’s example by donating land for road construction
From plots of land, rows of trees and boundary walls voluntarily donated by local residents, many roads in Hai Phong have been widened.
Hai Phong sets timeline for five key transport projects in city center
The Secretary of the Hai Phong Party Committee has ordered five major transport projects in the city center to be placed under special monitoring for progress, quality, and disbursement.
Hai Phong focuses on site clearance for Ring Road 3 key project
Hai Phong is expediting site clearance to keep Ring Road 3, the key transport component of its climate change adaption project, on schedule.
New Cay bridge completed, awaiting approach road opening
After more than two years of construction, the new Cay bridge spanning the Sat river on Provincial Road 394 linking Mao Dien and Binh Giang communes, has been completed and is awaiting opening to traffic.
Provincial Road 390B upgrading project to be completed before Dec
The project to upgrade Provincial Road 390B and build a bypass around the former Thanh Ha town center has a total investment of more than VND 720 billion.
Five transport procedures in Hai Phong to be processed through National Public Service Portal
Transport organizations and businesses in Hai Phong will submit online applications for five administrative procedures related to domestic road transport via the National Public Service Portal.
Road linking Provincial Roads 391 and 390 to break ground in Nov
The project to build a road linking Provincial Roads 391 and 390, with a total investment of more than VND1 trillion, is scheduled to break ground in November.