Hai Phong speeds up public investment disbursement towards year-end

Minh Khỏi • 25/11/2026 22:06

Public investment disbursement for 2026 is entering its final period, with Hai Phong striving to exceed the target of 20% above the capital allocation assigned by the Prime Minister.

Hai Thanh Bridge on Ring Road 2 is scheduled for the final joining of its bridge deck on November 26.

Key infrastructure project gathers pace

The construction package for the Ring Road 2 project, covering the Tan Vu – Hung Dao – Bui Vien Road section, spans more than 11 kilometers and has a total investment of over VND 8.593 trillion. In the final days of the year, contractors at the construction site are accelerating work, making the most of every hour and day to complete project components as scheduled. During implementation, the project encountered a number of challenges, including difficulties with site clearance, shortages of construction materials, contractors' capacity and adverse weather conditions.

However, thanks to the decisive involvement of the project investor and local authorities, major obstacles have gradually been addressed, enabling contractors to focus on construction. On November 26, Hai Thanh Bridge, currently the widest bridge in Hai Phong, is expected to reach the final joining stage. The remaining construction packages have all achieved more than 80% completion. Contractors are focusing on finishing the final items, striving to ensure construction quality and put the project into operation on January 31, 2027.

Accelerated construction has also helped speed up capital disbursement, with disbursement currently reaching 95% of the total capital allocated to the project.

The Nguyen Trai – Le Hong Phong multi-level interchange is accelerating construction to meet the target of completing the underpass before January 31, 2027. Photo: TRUNG KIEN

In response to the city's requirement to complete the road connecting Dinh Vu Industrial Park with Nam Dinh Vu Industrial Park (Phase II) before the 2027 New Year holiday, the construction contractor, Bach Dang Construction Corporation – JSC, has mobilized maximum manpower, materials and equipment since mid-November. It has also developed appropriate construction plans to ensure the project's progress.

A representative of the contractor said the project is being carried out while the road remains open to traffic, with a high volume of vehicles entering and leaving the port. This poses considerable pressure on the construction schedule, requiring all relevant units to maintain a high level of focus and organize construction activities flexibly and efficiently. As of mid-November 2026, only 21.7% of the allocated capital had been disbursed. However, with construction now being accelerated at the site, the contractor has pledged to achieve 100% disbursement of the capital allocated to the project by December 31.

In 2026, Hai Phong has identified public investment disbursement as a key driver of economic growth, infrastructure development and the creation of new development opportunities for the city. As of November 20, total public investment disbursement across the city had reached 101% of the target assigned by the Prime Minister, after excluding the 5% budget saving. With this result, Hai Phong ranked third nationwide in terms of disbursed public investment capital and was rated “Very Good” by the Ministry of Finance.

Notably, many project investors and local authorities have recorded high disbursement rates. Of the 125 project investors and local authorities, 78 had disbursed at least 86% of their allocated capital, with many exceeding 95%. Several wards and communes had achieved disbursement rates of over 95%, including An Phong, Chi Minh, Hong Chau, Kien Hung, Quyet Thang, Hung Dao, Do Son, Hai Duong, Phu Lien and Duong Kinh.

Prioritizing key projects and inter-regional connectivity

The road connecting Dinh Vu Industrial Park with Nam Dinh Vu Industrial Park (Phase II) must be completed before the 2027 New Year holiday. Photo: LE DUNG

To date, Hai Phong has disbursed 101% of the public investment capital allocated for 2026 by the Prime Minister. To achieve the target of exceeding the assigned plan by 20%, project investors have just over a month left to further accelerate disbursement. During inspections of construction progress, city leaders have consistently emphasized that speeding up disbursement must go hand in hand with accountability, regulatory compliance, construction quality and investment efficiency.

Following adjustments, the total public investment capital allocated for 2026 to the Hai Phong Transport Construction Investment Project Management Board has exceeded VND 14 trillion. As of November 20, the board had disbursed 81% of its allocated capital. To meet the set target, the board's leaders have regularly visited construction sites to inspect and urge progress, while promptly addressing difficulties and obstacles related to site clearance, material supplies and technical infrastructure.

At the same time, the board has instructed contractors to mobilize additional workers and machinery, deploy multiple construction teams and extend working hours and shifts. Contractors have also been asked to proactively adjust construction plans and make the most of favorable weather conditions to accelerate progress. Management and supervision are maintained on a regular and continuous basis, with implementation progress linked to the specific responsibilities of each division and individual official under the “six clear” principle.

Construction of Van Uc 2 Bridge on the Ninh Binh – Hai Phong Expressway.

Under a resolution adopted by the Hai Phong People's Council, the city's total public investment capital under its management for 2027 amounts to VND 38.76 trillion, excluding additional allocations. Against the backdrop of an expanding urban area and growing demand for connectivity, Hai Phong has identified strategic infrastructure projects as a priority for capital allocation, in line with the policies of the Politburo, the Government and the City Party Committee. These projects play an important role in restructuring the city's socio-economic space and contributing to its target of achieving 13% GRDP growth during the 2026–2030 period.

The city is prioritizing resources for a number of major transport projects, including the East–West Connector Road; the Hanoi – Quang Ninh high-speed railway; the Lao Cai – Hanoi – Hai Phong railway; Ring Road 3; the road linking Rao 3 Bridge with the coastal road section from Bui Vien Road to Provincial Road 363; and the coastal road through Hai Phong, running from Provincial Road 353 to Thai Binh Bridge (Km 0 – Km 19+645). These projects are all important to completing the transport network, strengthening regional connectivity and improving residents' quality of life.

With the resolve to “focus on action, not retreat” and the principle that “today's work must not be put off until tomorrow, and each issue must be addressed as it arises”, Hai Phong is mobilizing all available resources and determined to exceed by more than 20% the public investment capital target assigned by the Prime Minister. This achievement will provide further momentum for the city to enter 2027 with renewed determination to pursue even higher development goals.

In this final period, all projects, from major infrastructure developments to those at the local level, must not only accelerate construction progress but also ensure quality, safety and investment efficiency. Once completed, these projects will help improve the transport network, strengthen connectivity between economic regions, expand development space, attract investment and promote Hai Phong's socio-economic growth.

Minh Khoi

(0) Comment
Hai Phong speeds up public investment disbursement towards year-end