Removing site clearance bottlenecks for Thang Long industrial cluster
More than 12 hectares of land designated for infrastructure connectivity have yet to meet the legal requirements for land acquisition, causing prolonged site clearance delays at Thang Long Industrial Cluster and affecting the project’s overall progress.
News
Overcoming difficulties to maintain public investment disbursement momentum
In the first four months of 2026, Hai Phong’s public investment disbursement recorded positive results, helping to drive economic growth.
Accelerate site clearance for Tien Lang Airport Industrial Park – Zone B
The People’s Committee of Chan Hung Commune (Hai Phong) is striving to complete site clearance for the Tien Lang Airport Industrial Park – Zone B project in June 2026, ahead of the schedule.
An Phong eyes completion of site clearance for Trang Due supporting industrial cluster by Q2 2026
An Phong Ward in Hai Phong eyes completion of site clearance for the Trang Due Supporting Industrial Cluster project by the second quarter of 2026, local authorities said.
Phu Lien ward begins first compensation payments for National Highway 5–National Highway 10 connecting road project
Phu Lien Ward has made the first compensation payments for site clearance to households whose land is being acquired for the project connecting National Highway 5 with National Highway 10.
Preventing delays in site clearance for projects
To quickly unlock public investment capital, site clearance for projects must be directed decisively and implemented urgently.
Basically completing site clearance for Trang Due supporting industrial cluster
The Investment, Construction and Business Management Project for the technical infrastructure of the Trang Due supporting industrial cluster revokes more than 647,500 square meters of land.
Accelerating execution tempo of Hanh Phuc lake flower garden project
After multiple schedule adjustments due to site clearance issues and construction conditions, the Hanh Phuc lake flower garden project in Kien An Ward is entering its final phase, aiming to finish before the 2026 Lunar New Year.
Speeding up site clearance for industrial park projects
Vice Chairman of the Hai Phong People’s Committee Le Trung Kien has required faster site clearance for Trang Due 3 and An Duong industrial park investment projects.
Kien An to speed up site clearance and public investment disbursement
Standing Vice Chairman of the Hai Phong People’s Committee Le Anh Quan has required the Kien An Project Management Board to highly focus on public investment disbursement in the area.