45-day site clearance campaign for railway project
10 localities in eastern Hai Phong are required to complete site clearance for the Lao Cai – Ha Noi – Hai Phong railway project by the end of September 2026.
Business
First resettlement project for Lao Cai–Hanoi–Hai Phong railway completed
The Duong Kinh Resettlement Area has been completed, becoming the first resettlement project for the Lao Cai–Hanoi–Hai Phong railway to be finished.
More than VND 456 billion to build resettlement area in Do Son
A project to build a resettlement area to support site clearance in Do Son Ward and Nam Do Son Ward, Hai Phong city has a total investment of more than VND 456 billion.
Long-term vision for building resettlement areas
Hai Phong City is implementing many key projects that require large-scale land acquisition, necessitating a long-term vision for the development of resettlement areas.
Duong Kinh resettlement area races to completion
With the determination of local authorities, the efforts of contractors, and the consensus of residents, the Dương Kinh resettlement area is gradually taking shape.
Hai Phong completes site clearance for 15 resettlement areas serving railway project
Hai Phong has completed site clearance for 15 out of 22 resettlement areas serving the Lao Cai – Ha Noi – Hai Phong railway construction project passing through the city.