Hai Phong is urgently implementing four component projects to complete the Hai Phong – Ninh Binh Expressway, which is expected to open up new development space and drive economic growth.

Racing against time
At its fifth session in September 2026, the Hai Phong People's Council approved the project to build the Ninh Binh – Hai Phong Expressway (CT.08)’s section passing through Hai Phong and 9 km in Hung Yen Province, to complete the expressway and the connecting section to Provincial Road 353. The project has a total investment of more than VND 8.228 trillion and is scheduled for implementation from 2026 to 2029.
The Hai Phong Traffic Construction Investment Project Management Board is carrying out necessary procedures to commence the project in early 2027.
The project will complete CT.08 Expressway’s section from the interchange with the coastal road to the interchange with National Highway 37 in Hung Yen Province. The route will be approximately 24.19 km long, with four expressway lanes. It will also include the construction of service roads on both sides of the expressway within Hai Phong.
The section from the Ha Noi – Hai Phong Expressway to the coastal road interchange must be completed before December 31, 2027. The project owner is racing against time to carry out bidding procedures and approve the results of contractor selection.
On November 23, two main construction contractors for the project were approved. Regarding site clearance, Duong Kinh and Nam Do Son wards, as well as Kien Minh and Kien Hai communes, have been required to substantially complete site handover before December 31, 2026, ensuring that site clearance does not become a bottleneck. This is crucial for the project to break ground in January 2027.
Expanding interregional transport connectivity

The four component projects to complete CT.08 Expressway have a combined investment of more than VND 15.616 trillion. Once completed, the projects will connect expressways in Thanh Hoa, Ninh Binh and Hung Yen with Hai Phong and Quang Ninh, creating favorable conditions for attracting investment across various sectors and serving as a driving force for the development of Hai Phong's southern economic zone.
According to leaders of the Hai Phong Logistics Association, CT.08 Expressway will enable goods from the North Central provinces, Ninh Binh, Hung Yen and other areas to reach Hai Phong's ports more quickly, significantly reducing transport costs.
It will also open up development space and enhance the competitiveness of industrial parks and clusters along the route. This will create conditions for attracting new investment projects to coastal industrial parks, where land reserves remain substantial and infrastructure is being developed in a coordinated manner.
In particular, CT.08 Expressway is the missing link connecting the Eastern North–South Expressway with the expressway corridor toward Hai Phong. The route will allow provinces in the northern coastal region and North Central region to avoid detours and access the sea directly via an east–west transport axis, strengthening the “East–West economic corridor” linkage.
Construction of the main route of CT.08 Expressway through Ninh Binh and Hung Yen is being accelerated by the localities concerned. Alongside these localities, Hai Phong is proactively implementing its component projects, reviewing land reserves and investing in connecting infrastructure from the expressway to roads leading to the inner city, seaports and logistics centers.
With the requirement to put CT.08 projects in Hai Phong into operation by the end of 2027, the focus is now on rapidly turning progress into actual construction output, from sections temporarily open to traffic and active construction sites to packages preparing to break ground. Once completed, CT.08 Expressway will become a “gateway for connectivity,” opening up development space for Hai Phong, Ninh Binh, Hung Yen and other localities.
MINH KHOI