Hai Phong strives to fully disburse planned public investment by November 30
Vice Chairman of the Hai Phong People's Committee Le Trung Kien has called for full disbursement of the public investment allocated at the beginning of the year by November 30.

On November 17, Le Trung Kien, Member of the Standing Committee of the Hai Phong Party Committee and Vice Chairman of the City People's Committee, chaired a hybrid meeting, both in person and online, with departments, agencies, project owners, and 114 communes, wards, and special zones to review the progress of public investment disbursement and site clearance in November 2026.
In his concluding remarks, Vice Chairman Le Trung Kien acknowledged the efforts made by agencies and localities, which helped Hai Phong rank among the country's leading localities in terms of public investment disbursement.

He called on the entire political system to stay focus, striving to disburse 100% of the capital allocated at the beginning of the year by November 30, and the entire additional allocation in December 2026, in line with the direction of the Standing Committee of the City Party Committee.
The vice chairman assigned the Department of Finance to promptly advise on reallocating capital among projects and consider incorporating disbursement progress into the criteria for allocating capital in the following year.
The Department of Agriculture and Environment was tasked with coordinating with local authorities to urge investors of industrial park and cluster infrastructure projects to transfer site clearance funds and reviewing land-use fee calculations and the issuance of land-use rights certificates in resettlement areas. The Department of Construction was asked to accelerate the appraisal and licensing of projects.

The Department of Science and Technology was assigned to upgrade the Intelligent Operations Center, update detailed information on each project, attach QR codes to track progress, and establish automatic alerts for projects and localities falling behind schedule.
According to a report by the Department of Finance, by November 15, a total of VND 36.479 trillion in public investment had been disbursed across the city. Of this amount, VND 35.943 trillion came from the 2026 capital plan, equivalent to 93% of the target assigned by the Prime Minister.
Of the 221 public investment projects scheduled to complete site clearance in 2026, 155 have done so, with the total area cleared reaching 80.7%.